Bugok LNG Combined Cycle Power Plant (Unit #1)
- 구분
화력/원자력/신재생에너지
- 발주처
GS EPS
- 공사기간
1998.07~2000.08
- 국가/위치
Bugok, Korea
- 공사개요
- Total Capacity : 500MW
- Gas Turbine Generator (175MW X2)
- HRSG (3 Pressure, Indoor Type X2)
- Steam Turbine Generator ( 188MW x1)